Specification and component check
Confirm the ordered configuration, component list, machine appearance, welding and surfaces that were specified, guards, labels and drawing revisions before running tests.
- Configuration against order
- Component and material evidence
- Appearance and accessible surfaces
- Guards and labels
- Open deviations
Dry run and water test
Observe dry cycling, water operation, bottle transfer, washing sequence, filling, cap feeding and capping. Record utility conditions and identify differences from the final site.
- Dry cycle
- Water test
- Bottle transfer
- Filling result
- Cap feed and capping
Alarms, safety and capacity
Test selected alarms, no-bottle logic, blocked discharge, emergency stops and guard response. Capacity confirmation must use the agreed bottle, test window and acceptance rule.
- Alarm test
- Safety test
- Starved and blocked conditions
- Gross and saleable output
- Reject record
Documents, spares and packing
Close the FAT with documents, software or parameter backups where included, spare parts, punch-list ownership and packing inspection. Final FAT projects must be based on the contract and technical appendix confirmed by both parties.
- Signed FAT report
- Manuals and drawings
- Spare-parts check
- Punch-list closeout
- Packing and shipment release
Information needed for a quote
Send the bottle and cap basis, required BPH, bottle path, factory and utility information, destination and any module or support requirement. Unknown items can remain marked “to be confirmed.”