Normalize the proposal before selection
Issue the same bottle, cap, output, process boundary, utilities, destination and service requirement to every candidate. Compare inclusions and exclusions beside price, and request drawings or sample-testing evidence that relates to the proposed machine rather than generic promotion.
- One bottle and cap basis
- One output and operating basis
- Visible inclusions and exclusions
- Relevant drawing or sample evidence
- Open-point register
Check the specification and components
Confirm the ordered configuration, component list, machine appearance, specified welding and surfaces, guards, labels and drawing revisions before running tests.
- Configuration against order
- Component and material evidence
- Appearance and accessible surfaces
- Guards and labels
- Open deviations
Dry run and water test
Observe dry cycling, water operation, bottle transfer, washing sequence, filling, cap feeding and capping. Record utility conditions and identify differences from the final site.
- Dry cycle
- Water test
- Bottle transfer
- Filling result
- Cap feed and capping
Alarms, safety and capacity
Test selected alarms, no-bottle logic, blocked discharge, emergency stops and guard response. Capacity confirmation must use the agreed bottle, test window and acceptance rule.
- Alarm test
- Safety test
- Starved and blocked conditions
- Gross and saleable output
- Reject record
Close documents, spares and responsibility
Close the FAT with manuals, drawings, software or parameter backups where included, spare parts, punch-list ownership and packing inspection. Record installation, warranty and support boundaries in the agreement rather than relying on sales-language assumptions.
- Signed FAT report
- Manuals and drawings
- Spare-parts check
- Punch-list closeout
- Packing and support boundary
Information needed for a quote
Send the bottle and cap basis, required BPH, bottle path, factory and utility information, destination and any module or support requirement. Unknown items can remain marked “to be confirmed.”